RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 1604017040 - Archived data from Tue, 21. July 2020 14:43:23 CEST


This is all the information about APD 1604017040. If it is wrong, edit the data.

Subdetector specification:  
Serial: 1604017040
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: G05
Break-through voltage: 414 V
Voltage for Gain 100 (T=+25°C): 386.1 V
Dark current: 6.4 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 302
Position in Box: 1
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 439
Position in grid: 13
Arrival for irradiation: 30. Oct 2017
Sent for analysis after irradiation: 10. Nov 2017
Return for assembly: none
   
Irradiation:  
Date: 10. Nov 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 4
Bias voltage: 386.1 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 150: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 200: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 100: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 150: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 200: T = +20 °C: none     T = -25 °C: none
Break-through voltage: T = +20 °C: none     T = -25 °C: none
   
Notes:


Version history

Time Author Change comment
21. Apr 2021 12:51:23 CEST jreher Updated box and position via API.
05. Feb 2021 11:27:13 CET jreher Updated box and position via API.
11. Aug 2020 17:57:26 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:43:23 CEST jreher Updated APD location via API.
21. Jul 2020 14:43:13 CEST jreher Updated box and position via API.
19. Dec 2019 16:18:42 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:18:05 CET jreher Updated box and position via API.
10. Nov 2017 09:39:43 CET markus.moritz Entered shipped after irradiation date.
10. Nov 2017 09:38:15 CET markus.moritz Entered irradiation information.
09. Nov 2017 15:11:44 CET markus.moritz Entered arrival for irradiation date.
02. Nov 2017 15:16:56 CET Tobias Assigned to grid via information extracted from APD DB.
23. Jun 2016 10:42:24 CEST Tobias Imported from Hamamatsu datasheet.