Show Hamamatsu Avalanche Photo Diode 1604017037 - Archived data from Thu, 15. April 2021 17:00:52 CEST


This is all the information about APD 1604017037. If it is wrong, edit the data.

Subdetector specification:  
Serial: 1604017037
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D07
Break-through voltage: 417 V
Voltage for Gain 100 (T=+25°C): 387.7 V
Dark current: 5.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 301
Position in Box: 48
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 439
Position in grid: 10
Arrival for irradiation: 30. Oct 2017
Sent for analysis after irradiation: 10. Nov 2017
Return for assembly: none
   
Irradiation:  
Date: 10. Nov 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 4
Bias voltage: 387.7 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 388.6110528 V     T = -25 °C: 352.4098688 V
Voltage for Gain 150: T = +20 °C: 396.5698821 V     T = -25 °C: 359.9765002 V
Voltage for Gain 200: T = +20 °C: 400.970839 V     T = -25 °C: 364.2013981 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.323743213 V-1     T = -25 °C: 4.792510554 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.239288648 V-1     T = -25 °C: 8.711175401 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.3333717 V-1     T = -25 °C: 14.59036298 V-1
Break-through voltage: T = +20 °C: 416.3572402 V     T = -25 °C: 379.6524173 V
   
Notes:


Version history

Time Author Change comment
16. Nov 2021 09:30:51 CET oafedulidis Assigned to capsule by script
15. Apr 2021 17:00:52 CEST jreher Updated box and position via API.
05. Feb 2021 11:27:11 CET jreher Updated box and position via API.
11. Aug 2020 17:57:26 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:43:11 CEST jreher Updated APD location via API.
21. Jul 2020 14:43:02 CEST jreher Updated box and position via API.
19. Dec 2019 16:18:42 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:18:00 CET jreher Updated box and position via API.
10. Nov 2017 09:39:43 CET markus.moritz Entered shipped after irradiation date.
10. Nov 2017 09:38:15 CET markus.moritz Entered irradiation information.
09. Nov 2017 15:11:44 CET markus.moritz Entered arrival for irradiation date.
02. Nov 2017 15:16:56 CET Tobias Assigned to grid via information extracted from APD DB.
23. Jun 2016 10:42:24 CEST Tobias Imported from Hamamatsu datasheet.