RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 1413016037 - Archived data from Mon, 30. August 2021 14:07:25 CEST


This is all the information about APD 1413016037. If it is wrong, edit the data.

Subdetector specification:  
Serial: 1413016037
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C08
Break-through voltage: 419 V
Voltage for Gain 100 (T=+25°C): 390.2 V
Dark current: 5.3 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 309
Position in Box: 8
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 399
Position in grid: 13
Arrival for irradiation: 02. Nov 2017
Sent for analysis after irradiation: 03. Nov 2017
Return for assembly: none
   
Irradiation:  
Date: 03. Nov 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 4
Bias voltage: 390.2 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 390.9495787 V     T = -25 °C: 354.6093377 V
Voltage for Gain 150: T = +20 °C: 398.9008112 V     T = -25 °C: 362.2150636 V
Voltage for Gain 200: T = +20 °C: 403.3240027 V     T = -25 °C: 366.5071172 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.549924026 V-1     T = -25 °C: 4.690043159 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.94180724 V-1     T = -25 °C: 9.04050987 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 13.79541402 V-1     T = -25 °C: 15.81148643 V-1
Break-through voltage: T = +20 °C: 418.7246566 V     T = -25 °C: 382.0701435 V
   
Notes:


Version history

Time Author Change comment
15. Nov 2022 11:13:33 CET oafedulidis Assigned to capsule by script
30. Aug 2021 14:07:25 CEST oafedulidis Updated box and position via API.
05. Feb 2021 11:28:18 CET jreher Updated box and position via API.
11. Aug 2020 17:58:38 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:45:08 CEST jreher Updated APD location via API.
21. Jul 2020 14:44:59 CEST jreher Updated box and position via API.
19. Dec 2019 16:47:34 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:19:00 CET jreher Updated box and position via API.
03. Nov 2017 16:15:23 CET markus.moritz Entered shipped after irradiation date.
03. Nov 2017 16:14:44 CET markus.moritz Entered irradiation information.
02. Nov 2017 15:18:41 CET markus.moritz Entered arrival for irradiation date.
01. Aug 2016 17:29:30 CEST Tobias Assigned to grid via information extracted from APD DB.
23. Jun 2016 10:39:46 CEST Tobias Imported from Hamamatsu datasheet.