RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 1401015139 - Archived data from Thu, 19. December 2019 15:18:53 CET


This is all the information about APD 1401015139. If it is wrong, edit the data.

Subdetector specification:  
Serial: 1401015139
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: unknown
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: G06
Break-through voltage: 421 V
Voltage for Gain 100 (T=+25°C): 392.5 V
Dark current: 3.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 308
Position in Box: 17
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 358
Position in grid: 13
Arrival for irradiation: 29. Sep 2017
Sent for analysis after irradiation: 20. Oct 2017
Return for assembly: none
   
Irradiation:  
Date: 20. Oct 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 2
Bias voltage: 392.5 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 150: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 200: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 100: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 150: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 200: T = +20 °C: none     T = -25 °C: none
Break-through voltage: T = +20 °C: none     T = -25 °C: none
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:28:11 CET jreher Updated box and position via API.
11. Aug 2020 17:58:30 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:44:54 CEST jreher Updated APD location via API.
21. Jul 2020 14:44:45 CEST jreher Updated box and position via API.
19. Dec 2019 16:36:30 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:18:53 CET jreher Updated box and position via API.
20. Oct 2017 14:31:38 CEST markus.moritz Entered shipped after irradiation date.
20. Oct 2017 09:50:32 CEST markus.moritz Entered irradiation information.
29. Sep 2017 14:21:34 CEST markus.moritz Entered arrival for irradiation date.
01. Aug 2016 17:29:03 CEST Tobias Assigned to grid via information extracted from APD DB.
23. Jun 2016 10:31:16 CEST Tobias Imported from Hamamatsu datasheet.