RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 0915010069


This is all the information about APD 0915010069. If it is wrong, edit the data.

Subdetector specification:  
Serial: 0915010069
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: H09
Break-through voltage: 410 V
Voltage for Gain 100 (T=+25°C): 380.9 V
Dark current: 5.5 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 380
Position in Box: 10
EP1 batch: none
EP1 batch after irradiation: 10581
   
Shipment:  
Grid number: 222
Position in grid: 16
Arrival for irradiation: 15. Jun 2016
Sent for analysis after irradiation: 08. Jul 2016
Return for assembly: 04. Aug 2016
   
Irradiation:  
Date: 30. Jun 2016
Dose used: 30 Gy
Temperature: 25 °C
Position: 3
Bias voltage: 320 V     (connection unknown)
   
Annealing:  
Date: 01. Jul 2016
Temperature: 80 °C
Duration: 8 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 381.5296867 V     T = -25 °C: 345.978463 V
Voltage for Gain 150: T = +20 °C: 389.3920475 V     T = -25 °C: 353.357421 V
Voltage for Gain 200: T = +20 °C: 393.7570421 V     T = -25 °C: 357.5205551 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.431320441 V-1     T = -25 °C: 4.940724776 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.631261271 V-1     T = -25 °C: 9.172145408 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.99502004 V-1     T = -25 °C: 16.22857328 V-1
Break-through voltage: T = +20 °C: 408.9136695 V     T = -25 °C: 372.8540538 V
   
Notes:


Characteristics

Temperature Measurement Notes
No characteristics available!


Upload new characteristic...

Progression of the current during irradiation

Upload time Notes
No data available!


Upload new progression data...

Version history

Time Author Change comment
16. Apr 2021 22:03:09 CEST jreher Updated APD characteristics via API.
05. Feb 2021 11:37:03 CET jreher Updated box and position via API.
13. Oct 2020 16:50:14 CEST vwerner Updated APD batch assignment via API.
08. Oct 2020 18:19:59 CEST jreher Updated APD location via API.
04. Aug 2016 13:26:15 CEST markus.moritz Entered return for assembly date.
03. Aug 2016 16:41:33 CEST markus.moritz Entered irradiation information.
03. Aug 2016 16:15:06 CEST markus.moritz Entered shipped after irradiation date.
03. Aug 2016 16:14:57 CEST markus.moritz Entered arrival for irradiation date.
02. Aug 2016 14:52:11 CEST christopher.l.hahn Entered annealing information.
02. Aug 2016 14:50:36 CEST christopher.l.hahn Entered annealing information.
01. Aug 2016 17:27:45 CEST Tobias Assigned to grid via information extracted from APD DB.
23. Jun 2016 10:26:43 CEST Tobias Imported from Hamamatsu datasheet.