RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 1305013839 - Archived data from Wed, 03. February 2021 18:07:10 CET


This is all the information about APD 1305013839. If it is wrong, edit the data.

Subdetector specification:  
Serial: 1305013839
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: In transit to Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D15
Break-through voltage: 440 V
Voltage for Gain 100 (T=+25°C): 414.6 V
Dark current: 11.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 416
Position in Box: 44
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 300
Position in grid: 12
Arrival for irradiation: 29. Sep 2017
Sent for analysis after irradiation: 03. Nov 2017
Return for assembly: none
   
Irradiation:  
Date: 26. Oct 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 1
Bias voltage: 414.6 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 150: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 200: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 100: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 150: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 200: T = +20 °C: none     T = -25 °C: none
Break-through voltage: T = +20 °C: none     T = -25 °C: none
   
Notes:


Version history

Time Author Change comment
16. Apr 2021 22:09:03 CEST jreher Updated APD characteristics via API.
16. Apr 2021 10:28:52 CEST jreher Updated APD location via API.
31. Mar 2021 14:14:56 CEST jreher Updated box and position via API.
26. Feb 2021 15:45:00 CET jreher Updated APD batch assignment via API.
03. Feb 2021 18:07:10 CET jreher Updated APD location via API.
03. Nov 2017 16:12:38 CET markus.moritz Entered shipped after irradiation date.
26. Oct 2017 16:35:47 CEST markus.moritz Entered irradiation information.
29. Sep 2017 14:20:10 CEST markus.moritz Entered arrival for irradiation date.
01. Aug 2016 17:28:24 CEST Tobias Assigned to grid via information extracted from APD DB.
22. Jun 2016 15:40:58 CEST Tobias Imported from Hamamatsu datasheet.