Show Hamamatsu Avalanche Photo Diode 0816008447 - Archived data from Tue, 11. August 2020 17:59:02 CEST


This is all the information about APD 0816008447. If it is wrong, edit the data.

Subdetector specification:  
Serial: 0816008447
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E11
Break-through voltage: 415 V
Voltage for Gain 100 (T=+25°C): 387.1 V
Dark current: 4.5 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 311
Position in Box: 31
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 64
Position in grid: 18
Arrival for irradiation: 03. Aug 2017
Sent for analysis after irradiation: 17. Aug 2017
Return for assembly: none
   
Irradiation:  
Date: 10. Aug 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 1
Bias voltage: 387.1 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 387.5141415 V     T = -25 °C: 351.2649752 V
Voltage for Gain 150: T = +20 °C: 395.4568139 V     T = -25 °C: 358.8313532 V
Voltage for Gain 200: T = +20 °C: 399.846163 V     T = -25 °C: 363.075935 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.394201609 V-1     T = -25 °C: 4.710705869 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.512072654 V-1     T = -25 °C: 9.434586635 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.73052916 V-1     T = -25 °C: 14.70420097 V-1
Break-through voltage: T = +20 °C: 415.2416302 V     T = -25 °C: 378.5970613 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:28:36 CET jreher Updated box and position via API.
11. Aug 2020 17:59:02 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:45:36 CEST jreher Updated APD location via API.
21. Jul 2020 14:45:30 CEST jreher Updated box and position via API.
28. Jan 2020 14:22:09 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:19:17 CET jreher Updated box and position via API.
23. Aug 2017 16:04:33 CEST markus.moritz Entered shipped after irradiation date.
10. Aug 2017 15:08:36 CEST hans-georg.zaunick Entered irradiation information.
07. Aug 2017 16:53:58 CEST hans-georg.zaunick Entered arrival for irradiation date.
07. Aug 2017 16:45:09 CEST hans-georg.zaunick Entered arrival for irradiation date.
04. Aug 2017 03:15:05 CEST Tobias Assigned to grid via information extracted from APD DB.
22. Jun 2016 15:27:51 CEST Tobias Imported from Hamamatsu datasheet.