RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 0814008268 - Archived data from Tue, 21. July 2020 14:42:17 CEST


This is all the information about APD 0814008268. If it is wrong, edit the data.

Subdetector specification:  
Serial: 0814008268
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: unknown
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C14
Break-through voltage: 426 V
Voltage for Gain 100 (T=+25°C): 397.5 V
Dark current: 3.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 298
Position in Box: 32
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 68
Position in grid: 19
Arrival for irradiation: 03. Aug 2017
Sent for analysis after irradiation: 17. Aug 2017
Return for assembly: none
   
Irradiation:  
Date: 09. Aug 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 1
Bias voltage: 397.5 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 150: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 200: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 100: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 150: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 200: T = +20 °C: none     T = -25 °C: none
Break-through voltage: T = +20 °C: none     T = -25 °C: none
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:26:45 CET jreher Updated box and position via API.
11. Aug 2020 17:56:52 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:42:27 CEST jreher Updated APD location via API.
21. Jul 2020 14:42:17 CEST jreher Updated box and position via API.
19. Dec 2019 15:49:38 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:17:37 CET jreher Updated box and position via API.
23. Aug 2017 16:06:28 CEST markus.moritz Entered shipped after irradiation date.
09. Aug 2017 14:28:53 CEST hans-georg.zaunick Entered irradiation information.
07. Aug 2017 16:54:31 CEST hans-georg.zaunick Entered arrival for irradiation date.
07. Aug 2017 16:47:19 CEST hans-georg.zaunick Entered arrival for irradiation date.
04. Aug 2017 03:15:08 CEST Tobias Assigned to grid via information extracted from APD DB.
22. Jun 2016 15:27:47 CEST Tobias Imported from Hamamatsu datasheet.