RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 0810007949 - Archived data from Tue, 11. August 2020 17:56:27 CEST


This is all the information about APD 0810007949. If it is wrong, edit the data.

Subdetector specification:  
Serial: 0810007949
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D07
Break-through voltage: 407 V
Voltage for Gain 100 (T=+25°C): 378.6 V
Dark current: 6 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 296
Position in Box: 5
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 102
Position in grid: 6
Arrival for irradiation: 03. Aug 2017
Sent for analysis after irradiation: 23. Aug 2017
Return for assembly: none
   
Irradiation:  
Date: 10. Aug 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 2
Bias voltage: 378.6 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 379.0144518 V     T = -25 °C: 343.4847395 V
Voltage for Gain 150: T = +20 °C: 386.8757081 V     T = -25 °C: 350.8113706 V
Voltage for Gain 200: T = +20 °C: 391.2594577 V     T = -25 °C: 354.925485 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.57149308 V-1     T = -25 °C: 4.749414517 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.109480995 V-1     T = -25 °C: 9.74017144 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.10496108 V-1     T = -25 °C: 15.50990219 V-1
Break-through voltage: T = +20 °C: 407.1046184 V     T = -25 °C: 370.4681219 V
   
Notes:


Version history

Time Author Change comment
17. Jun 2021 18:45:22 CEST oafedulidis Assigned to capsule by script
05. Feb 2021 11:26:27 CET jreher Updated box and position via API.
18. Dec 2020 14:01:20 CET jreher Updated box and position via API.
11. Aug 2020 17:56:27 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:41:55 CEST jreher Updated APD location via API.
21. Jul 2020 14:41:46 CEST jreher Updated box and position via API.
19. Dec 2019 15:46:11 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:17:19 CET jreher Updated box and position via API.
23. Aug 2017 15:54:49 CEST markus.moritz Entered shipped after irradiation date.
10. Aug 2017 16:42:43 CEST hans-georg.zaunick Entered irradiation information.
07. Aug 2017 17:00:42 CEST hans-georg.zaunick Entered arrival for irradiation date.
04. Aug 2017 03:15:27 CEST Tobias Assigned to grid via information extracted from APD DB.
22. Jun 2016 15:26:13 CEST Tobias Imported from Hamamatsu datasheet.