RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 3312036135 - Archived data from Tue, 11. August 2020 18:02:13 CEST


This is all the information about APD 3312036135. If it is wrong, edit the data.

Subdetector specification:  
Serial: 3312036135
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: B08
Break-through voltage: 411 V
Voltage for Gain 100 (T=+25°C): 382.7 V
Dark current: 22.5 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 152
Position in Box: 4
EP1 batch: 178
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 382.9463943 V     T = -25 °C: 348.1964884 V
Voltage for Gain 150: T = +20 °C: 390.7371681 V     T = -25 °C: 355.5685031 V
Voltage for Gain 200: T = +20 °C: 395.0508798 V     T = -25 °C: 359.7225896 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.535072989 V-1     T = -25 °C: 5.088885216 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.336868649 V-1     T = -25 °C: 8.879564013 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.63489567 V-1     T = -25 °C: 16.42613218 V-1
Break-through voltage: T = +20 °C: 409.9669955 V     T = -25 °C: 374.2844894 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:07:49 CET jreher Updated box and position via API.
11. Aug 2020 18:02:13 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:52:08 CEST jreher Updated APD location via API.
03. Feb 2020 14:24:24 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:49:18 CET jreher Updated APD location via API.
27. Nov 2019 19:55:41 CET jreher Updated APD location via API.
25. Nov 2019 17:22:52 CET jreher Updated box and position via API.
26. Sep 2019 15:32:34 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:56:24 CEST jreher Updated APD location via API.
03. Jan 2019 00:15:21 CET Tobias Corrected dark current unit.
19. Sep 2018 14:05:31 CEST Tobias Imported from Hamamatsu datasheet.