RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 3211035255 - Archived data from Tue, 11. August 2020 17:54:46 CEST


This is all the information about APD 3211035255. If it is wrong, edit the data.

Subdetector specification:  
Serial: 3211035255
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C12
Break-through voltage: 413 V
Voltage for Gain 100 (T=+25°C): 385.3 V
Dark current: 22.3 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 140
Position in Box: 14
EP1 batch: 161
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 385.4471875 V     T = -25 °C: 349.4729945 V
Voltage for Gain 150: T = +20 °C: 393.297416 V     T = -25 °C: 356.9293647 V
Voltage for Gain 200: T = +20 °C: 397.6548374 V     T = -25 °C: 361.1268367 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.419556411 V-1     T = -25 °C: 4.689347439 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.704567092 V-1     T = -25 °C: 9.417954075 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.17570303 V-1     T = -25 °C: 14.7951531 V-1
Break-through voltage: T = +20 °C: 412.3538652 V     T = -25 °C: 375.9120145 V
   
Notes:


Version history

Time Author Change comment
26. Oct 2021 10:34:14 CEST oafedulidis Assigned to capsule by script
15. Apr 2021 17:01:23 CEST jreher Updated box and position via API.
05. Feb 2021 11:06:22 CET jreher Updated box and position via API.
11. Aug 2020 17:54:46 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:51:18 CEST jreher Updated APD location via API.
12. Dec 2019 14:42:33 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:48:36 CET jreher Updated APD location via API.
27. Nov 2019 19:53:33 CET jreher Updated APD location via API.
25. Nov 2019 17:21:59 CET jreher Updated box and position via API.
20. Sep 2019 18:48:18 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:54:57 CEST jreher Updated APD location via API.
03. Jan 2019 00:15:02 CET Tobias Corrected dark current unit.
14. Aug 2018 16:04:22 CEST Tobias Imported from Hamamatsu datasheet.