RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 3116034719 - Archived data from Tue, 11. August 2020 17:54:03 CEST


This is all the information about APD 3116034719. If it is wrong, edit the data.

Subdetector specification:  
Serial: 3116034719
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: F02
Break-through voltage: 406 V
Voltage for Gain 100 (T=+25°C): 381.1 V
Dark current: 12.9 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 131
Position in Box: 49
EP1 batch: 148
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 380.9756711 V     T = -25 °C: 345.9917618 V
Voltage for Gain 150: T = +20 °C: 388.8316482 V     T = -25 °C: 353.3422038 V
Voltage for Gain 200: T = +20 °C: 393.1996452 V     T = -25 °C: 357.4835283 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.629852247 V-1     T = -25 °C: 4.954600133 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.165486885 V-1     T = -25 °C: 9.225496132 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.1605465 V-1     T = -25 °C: 16.35366298 V-1
Break-through voltage: T = +20 °C: 404.6189995 V     T = -25 °C: 371.7648831 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:05:19 CET jreher Updated box and position via API.
11. Aug 2020 17:54:03 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:50:43 CEST jreher Updated APD location via API.
09. Dec 2019 18:15:29 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:48:07 CET jreher Updated APD location via API.
27. Nov 2019 19:51:58 CET jreher Updated APD location via API.
25. Nov 2019 17:21:22 CET jreher Updated box and position via API.
17. Sep 2019 11:36:05 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:53:52 CEST jreher Updated APD location via API.
03. Jan 2019 00:14:49 CET Tobias Corrected dark current unit.
14. Aug 2018 16:04:15 CEST Tobias Imported from Hamamatsu datasheet.