RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 3103034049 - Archived data from Tue, 11. August 2020 18:00:47 CEST


This is all the information about APD 3103034049. If it is wrong, edit the data.

Subdetector specification:  
Serial: 3103034049
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: F13
Break-through voltage: 415 V
Voltage for Gain 100 (T=+25°C): 386.9 V
Dark current: 17.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 122
Position in Box: 25
EP1 batch: 133
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 386.1553417 V     T = -25 °C: 351.2882346 V
Voltage for Gain 150: T = +20 °C: 394.0948263 V     T = -25 °C: 358.6276495 V
Voltage for Gain 200: T = +20 °C: 398.5090278 V     T = -25 °C: 362.7416761 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.452706076 V-1     T = -25 °C: 4.811654455 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.698119049 V-1     T = -25 °C: 9.818846164 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.08537665 V-1     T = -25 °C: 15.44371123 V-1
Break-through voltage: T = +20 °C: 413.7119816 V     T = -25 °C: 377.3981994 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:04:08 CET jreher Updated box and position via API.
11. Aug 2020 18:00:47 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:49:59 CEST jreher Updated APD location via API.
28. Jan 2020 16:13:57 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:47:32 CET jreher Updated APD location via API.
27. Nov 2019 19:50:17 CET jreher Updated APD location via API.
25. Nov 2019 17:20:37 CET jreher Updated box and position via API.
30. Aug 2019 11:30:08 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:52:38 CEST jreher Updated APD location via API.
03. Jan 2019 00:14:33 CET Tobias Corrected dark current unit.
06. Jul 2018 22:38:54 CEST Tobias Imported from Hamamatsu datasheet.