Subdetector specification:  
Serial: 3102033913
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: G06
Break-through voltage: 404 V
Voltage for Gain 100 (T=+25°C): 378.4 V
Dark current: 21.1 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 120
Position in Box: 42
EP1 batch: 130
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 377.304193 V     T = -25 °C: 342.4870253 V
Voltage for Gain 150: T = +20 °C: 385.0921333 V     T = -25 °C: 349.7391006 V
Voltage for Gain 200: T = +20 °C: 389.4283214 V     T = -25 °C: 353.7977601 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.587753807 V-1     T = -25 °C: 4.902300018 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.058364599 V-1     T = -25 °C: 10.09759826 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.21100194 V-1     T = -25 °C: 16.29544794 V-1
Break-through voltage: T = +20 °C: 404.3722115 V     T = -25 °C: 368.4076 V
   
Notes:


Version history

Time Author Change comment
17. Jun 2021 19:18:48 CEST oafedulidis Assigned to capsule by script
16. Feb 2021 12:28:16 CET jreher Updated box and position via API.
05. Feb 2021 11:03:54 CET jreher Updated box and position via API.
11. Aug 2020 18:07:34 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:49:52 CEST jreher Updated APD location via API.
06. Mar 2020 13:54:14 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:47:26 CET jreher Updated APD location via API.
27. Nov 2019 19:49:56 CET jreher Updated APD location via API.
25. Nov 2019 17:20:29 CET jreher Updated box and position via API.
30. Aug 2019 11:25:29 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:52:23 CEST jreher Updated APD location via API.
03. Jan 2019 00:14:31 CET Tobias Corrected dark current unit.
06. Jul 2018 22:38:53 CEST Tobias Imported from Hamamatsu datasheet.