RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 3101033856 - Archived data from Tue, 11. August 2020 18:07:27 CEST


This is all the information about APD 3101033856. If it is wrong, edit the data.

Subdetector specification:  
Serial: 3101033856
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C07
Break-through voltage: 410 V
Voltage for Gain 100 (T=+25°C): 381.2 V
Dark current: 18 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 120
Position in Box: 8
EP1 batch: 129
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 381.3207234 V     T = -25 °C: 346.1228597 V
Voltage for Gain 150: T = +20 °C: 389.1339864 V     T = -25 °C: 353.4226276 V
Voltage for Gain 200: T = +20 °C: 393.4827174 V     T = -25 °C: 357.5072336 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.49538467 V-1     T = -25 °C: 4.910015045 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.761208437 V-1     T = -25 °C: 9.059931296 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.25319959 V-1     T = -25 °C: 16.11702445 V-1
Break-through voltage: T = +20 °C: 409.2129192 V     T = -25 °C: 372.8977506 V
   
Notes:


Version history

Time Author Change comment
25. Oct 2021 14:14:20 CEST oafedulidis Assigned to capsule by script
15. Apr 2021 17:01:08 CEST jreher Updated box and position via API.
05. Feb 2021 11:03:51 CET jreher Updated box and position via API.
11. Aug 2020 18:07:27 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:49:49 CEST jreher Updated APD location via API.
02. Mar 2020 16:43:08 CET vwerner Updated APD batch assignment via API.
29. Nov 2019 11:47:23 CET jreher Updated APD location via API.
27. Nov 2019 19:49:54 CET jreher Updated APD location via API.
25. Nov 2019 17:20:26 CET jreher Updated box and position via API.
30. Aug 2019 11:26:49 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:52:20 CEST jreher Updated APD location via API.
03. Jan 2019 00:14:30 CET Tobias Corrected dark current unit.
06. Jul 2018 22:38:52 CEST Tobias Imported from Hamamatsu datasheet.