RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 3006033568 - Archived data from Tue, 11. August 2020 18:06:57 CEST


This is all the information about APD 3006033568. If it is wrong, edit the data.

Subdetector specification:  
Serial: 3006033568
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: B04
Break-through voltage: 418 V
Voltage for Gain 100 (T=+25°C): 391.9 V
Dark current: 17.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 116
Position in Box: 11
EP1 batch: 123
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 391.9838216 V     T = -25 °C: 356.0042814 V
Voltage for Gain 150: T = +20 °C: 399.8233164 V     T = -25 °C: 363.5952274 V
Voltage for Gain 200: T = +20 °C: 404.1664219 V     T = -25 °C: 367.825631 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.64992982 V-1     T = -25 °C: 4.795295378 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.245245735 V-1     T = -25 °C: 8.823127418 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.53895557 V-1     T = -25 °C: 15.57581511 V-1
Break-through voltage: T = +20 °C: 418.6864894 V     T = -25 °C: 382.7745584 V
   
Notes:


Version history

Time Author Change comment
27. Sep 2021 16:13:21 CEST oafedulidis Assigned to capsule by script
17. May 2021 09:17:54 CEST oafedulidis Updated box and position via API.
05. Feb 2021 11:03:20 CET jreher Updated box and position via API.
11. Aug 2020 18:06:57 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:49:31 CEST jreher Updated APD location via API.
02. Mar 2020 16:10:06 CET vwerner Updated APD batch assignment via API.
29. Nov 2019 11:47:08 CET jreher Updated APD location via API.
27. Nov 2019 19:49:09 CET jreher Updated APD location via API.
25. Nov 2019 17:20:07 CET jreher Updated box and position via API.
27. Aug 2019 12:09:35 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:51:48 CEST jreher Updated APD location via API.
03. Jan 2019 00:14:23 CET Tobias Corrected dark current unit.
06. Jul 2018 22:38:49 CEST Tobias Imported from Hamamatsu datasheet.