RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 3004033422 - Archived data from Tue, 11. August 2020 18:06:37 CEST


This is all the information about APD 3004033422. If it is wrong, edit the data.

Subdetector specification:  
Serial: 3004033422
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E06
Break-through voltage: 414 V
Voltage for Gain 100 (T=+25°C): 386.9 V
Dark current: 23.5 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 114
Position in Box: 9
EP1 batch: 119
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 386.3121885 V     T = -25 °C: 350.5590759 V
Voltage for Gain 150: T = +20 °C: 394.1462996 V     T = -25 °C: 358.0001238 V
Voltage for Gain 200: T = +20 °C: 398.5037328 V     T = -25 °C: 362.1793934 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.503423634 V-1     T = -25 °C: 4.658515917 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.808407934 V-1     T = -25 °C: 9.359726755 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.32588557 V-1     T = -25 °C: 14.65031551 V-1
Break-through voltage: T = +20 °C: 413.3944493 V     T = -25 °C: 376.9792195 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:03:03 CET jreher Updated box and position via API.
11. Aug 2020 18:06:37 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:49:21 CEST jreher Updated APD location via API.
25. Feb 2020 16:45:19 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:47:00 CET jreher Updated APD location via API.
27. Nov 2019 19:48:47 CET jreher Updated APD location via API.
25. Nov 2019 17:19:56 CET jreher Updated box and position via API.
27. Aug 2019 12:10:59 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:51:32 CEST jreher Updated APD location via API.
03. Jan 2019 00:14:20 CET Tobias Corrected dark current unit.
06. Jul 2018 22:38:47 CEST Tobias Imported from Hamamatsu datasheet.