Show Hamamatsu Avalanche Photo Diode 2909033088 - Archived data from Tue, 11. August 2020 18:05:16 CEST


This is all the information about APD 2909033088. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2909033088
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D05
Break-through voltage: 411 V
Voltage for Gain 100 (T=+25°C): 382.8 V
Dark current: 6.5 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 99
Position in Box: 7
EP1 batch: 95
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 382.7861376 V     T = -25 °C: 347.0761593 V
Voltage for Gain 150: T = +20 °C: 390.5883021 V     T = -25 °C: 354.46926 V
Voltage for Gain 200: T = +20 °C: 394.9068401 V     T = -25 °C: 358.6255185 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.412868056 V-1     T = -25 °C: 4.929896026 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.617462938 V-1     T = -25 °C: 9.148659824 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.14095972 V-1     T = -25 °C: 16.46980835 V-1
Break-through voltage: T = +20 °C: 409.868124 V     T = -25 °C: 373.5741978 V
   
Notes:


Version history

Time Author Change comment
17. Jun 2021 19:04:14 CEST oafedulidis Assigned to capsule by script
16. Feb 2021 12:27:29 CET jreher Updated box and position via API.
05. Feb 2021 11:01:06 CET jreher Updated box and position via API.
11. Aug 2020 18:05:16 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:55:33 CEST jreher Updated APD location via API.
17. Feb 2020 17:49:37 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:51:00 CET jreher Updated APD location via API.
27. Nov 2019 19:46:27 CET jreher Updated APD location via API.
25. Nov 2019 17:18:48 CET jreher Updated box and position via API.
24. Oct 2019 12:38:14 CEST spankonin Updated APD location via API.
20. Aug 2019 12:45:43 CEST jgrochowski Updated APD batch assignment via API.
03. Jan 2019 00:14:04 CET Tobias Corrected dark current unit.
20. Jun 2018 13:36:31 CEST Tobias Imported from Hamamatsu datasheet.