Show Hamamatsu Avalanche Photo Diode 2905032771 - Archived data from Tue, 11. August 2020 17:59:34 CEST


This is all the information about APD 2905032771. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2905032771
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C06
Break-through voltage: 412 V
Voltage for Gain 100 (T=+25°C): 383.4 V
Dark current: 8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 103
Position in Box: 16
EP1 batch: 101
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 383.5030967 V     T = -25 °C: 347.925895 V
Voltage for Gain 150: T = +20 °C: 391.3300688 V     T = -25 °C: 355.3693153 V
Voltage for Gain 200: T = +20 °C: 395.6792401 V     T = -25 °C: 359.5431737 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.450370889 V-1     T = -25 °C: 4.939445283 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.779661298 V-1     T = -25 °C: 9.09360389 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.37422537 V-1     T = -25 °C: 16.28922206 V-1
Break-through voltage: T = +20 °C: 411.1803651 V     T = -25 °C: 374.9614639 V
   
Notes:


Version history

Time Author Change comment
29. Mar 2022 12:35:58 CEST oafedulidis Assigned to capsule by script
17. May 2021 09:16:40 CEST oafedulidis Updated box and position via API.
05. Feb 2021 11:01:37 CET jreher Updated box and position via API.
11. Aug 2020 17:59:34 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:48:40 CEST jreher Updated APD location via API.
28. Jan 2020 14:54:10 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:46:20 CET jreher Updated APD location via API.
27. Nov 2019 19:46:56 CET jreher Updated APD location via API.
25. Nov 2019 17:19:07 CET jreher Updated box and position via API.
20. Aug 2019 12:48:32 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:50:21 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:57 CET Tobias Corrected dark current unit.
20. Jun 2018 13:36:21 CEST Tobias Imported from Hamamatsu datasheet.