RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2818032198 - Archived data from Tue, 11. August 2020 18:05:04 CEST


This is all the information about APD 2818032198. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2818032198
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: F07
Break-through voltage: 406 V
Voltage for Gain 100 (T=+25°C): 377.5 V
Dark current: 9.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 97
Position in Box: 46
EP1 batch: 93
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 377.32934 V     T = -25 °C: 342.2821153 V
Voltage for Gain 150: T = +20 °C: 385.1051262 V     T = -25 °C: 349.5616134 V
Voltage for Gain 200: T = +20 °C: 389.4533802 V     T = -25 °C: 353.6278115 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.558349243 V-1     T = -25 °C: 4.880083035 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.975663916 V-1     T = -25 °C: 9.135272712 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.74212588 V-1     T = -25 °C: 16.36930432 V-1
Break-through voltage: T = +20 °C: 404.9141671 V     T = -25 °C: 368.5947622 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:00:54 CET jreher Updated box and position via API.
11. Aug 2020 18:05:04 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:55:27 CEST jreher Updated APD location via API.
17. Feb 2020 17:50:26 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:50:55 CET jreher Updated APD location via API.
27. Nov 2019 19:46:08 CET jreher Updated APD location via API.
25. Nov 2019 17:18:42 CET jreher Updated box and position via API.
20. Aug 2019 12:44:23 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:49:11 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:55 CET Tobias Corrected dark current unit.
20. Jun 2018 13:36:19 CEST Tobias Imported from Hamamatsu datasheet.