RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2808031439 - Archived data from Tue, 11. August 2020 17:39:27 CEST


This is all the information about APD 2808031439. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2808031439
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C08
Break-through voltage: 412 V
Voltage for Gain 100 (T=+25°C): 384 V
Dark current: 9.9 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 88
Position in Box: 23
EP1 batch: 77
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 384.5144832 V     T = -25 °C: 348.8459573 V
Voltage for Gain 150: T = +20 °C: 392.350955 V     T = -25 °C: 356.2282149 V
Voltage for Gain 200: T = +20 °C: 396.6869716 V     T = -25 °C: 360.3709818 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.448343746 V-1     T = -25 °C: 4.962196407 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.678358694 V-1     T = -25 °C: 9.246428075 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.13778925 V-1     T = -25 °C: 14.5635118 V-1
Break-through voltage: T = +20 °C: 411.5971378 V     T = -25 °C: 375.0514558 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:59:40 CET jreher Updated box and position via API.
03. Feb 2021 18:25:09 CET jreher Updated box and position via API.
11. Aug 2020 17:39:27 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:44:26 CET jreher Updated APD location via API.
25. Nov 2019 17:17:55 CET jreher Updated box and position via API.
13. Sep 2019 10:30:23 CEST jgrochowski Updated APD batch assignment via API.
04. Sep 2019 12:47:30 CEST markus.moritz
25. Jul 2019 12:11:10 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:47:57 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:39 CET Tobias Corrected dark current unit.
20. Jun 2018 13:35:57 CEST Tobias Imported from Hamamatsu datasheet.