RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2804031075 - Archived data from Wed, 03. February 2021 18:24:50 CET


This is all the information about APD 2804031075. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2804031075
Type: Hamamatsu Avalanche Photo Diode
Detector: assigned to 2804031075/2313025279
Unit: #1082 (barcode 1309012015)
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: blue
   
Manufacturer information:  
Wafer position: E04
Break-through voltage: 406 V
Voltage for Gain 100 (T=+25°C): 377.6 V
Dark current: 7.8 nA
   
Screening Logistics:  
Available: No
Storage Box: 85
Position in Box: 39
EP1 batch: 73
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 377.5929252 V     T = -25 °C: 342.5109551 V
Voltage for Gain 150: T = +20 °C: 385.4270189 V     T = -25 °C: 349.8386369 V
Voltage for Gain 200: T = +20 °C: 389.7903665 V     T = -25 °C: 353.9530719 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.426509187 V-1     T = -25 °C: 4.758252874 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.573297245 V-1     T = -25 °C: 9.705310843 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.82212339 V-1     T = -25 °C: 15.36747499 V-1
Break-through voltage: T = +20 °C: 405.6671272 V     T = -25 °C: 369.4719439 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:59:20 CET jreher Updated box and position via API.
03. Feb 2021 18:24:50 CET jreher Updated box and position via API.
11. Aug 2020 17:39:06 CEST jreher Updated APD characteristics via API.
03. Apr 2020 09:46:53 CEST jreher Assigned to capsule by script
13. Feb 2020 14:23:50 CET jreher Updated box and position via API.
27. Nov 2019 19:43:56 CET jreher Updated APD location via API.
25. Nov 2019 17:17:40 CET jreher Updated box and position via API.
13. Sep 2019 10:29:15 CEST jgrochowski Updated APD batch assignment via API.
04. Sep 2019 13:26:35 CEST markus.moritz
25. Jul 2019 12:12:16 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:47:35 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:34 CET Tobias Corrected dark current unit.
24. May 2018 14:39:23 CEST Tobias Updated location to "Bochum".
18. May 2018 12:05:35 CEST Tobias Imported from Hamamatsu datasheet.