RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2802030935 - Archived data from Fri, 05. February 2021 10:59:11 CET


This is all the information about APD 2802030935. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2802030935
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E08
Break-through voltage: 402 V
Voltage for Gain 100 (T=+25°C): 376.6 V
Dark current: 7.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 64
Position in Box: 39
EP1 batch: 71
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 376.6021184 V     T = -25 °C: 341.6055705 V
Voltage for Gain 150: T = +20 °C: 384.3719766 V     T = -25 °C: 348.8597003 V
Voltage for Gain 200: T = +20 °C: 388.7066872 V     T = -25 °C: 352.9297362 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.455191378 V-1     T = -25 °C: 4.766602478 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.676183847 V-1     T = -25 °C: 9.75674136 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.0236033 V-1     T = -25 °C: 15.50708327 V-1
Break-through voltage: T = +20 °C: 404.4395565 V     T = -25 °C: 368.0005187 V
   
Notes:


Version history

Time Author Change comment
03. May 2021 10:25:07 CEST oafedulidis Updated box and position via API.
05. Feb 2021 10:59:11 CET jreher Updated box and position via API.
03. Feb 2021 18:24:40 CET jreher Updated box and position via API.
11. Aug 2020 17:38:55 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:43:44 CET jreher Updated APD location via API.
25. Nov 2019 17:17:34 CET jreher Updated box and position via API.
13. Sep 2019 10:28:30 CEST jgrochowski Updated APD batch assignment via API.
04. Sep 2019 13:03:45 CEST markus.moritz
25. Jul 2019 12:12:46 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:47:27 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:32 CET Tobias Corrected dark current unit.
24. May 2018 14:39:23 CEST Tobias Updated location to "Bochum".
18. May 2018 12:05:10 CEST Tobias Imported from Hamamatsu datasheet.