RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2801030844 - Archived data from Wed, 03. February 2021 18:24:34 CET


This is all the information about APD 2801030844. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2801030844
Type: Hamamatsu Avalanche Photo Diode
Detector: assigned to 2508028141/2801030844
Unit: #1341 (barcode 1309015085)
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: red
   
Manufacturer information:  
Wafer position: E08
Break-through voltage: 406 V
Voltage for Gain 100 (T=+25°C): 377.9 V
Dark current: 5.1 nA
   
Screening Logistics:  
Available: No
Storage Box: 83
Position in Box: 38
EP1 batch: 70
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 378.4116058 V     T = -25 °C: 343.3807499 V
Voltage for Gain 150: T = +20 °C: 386.2551439 V     T = -25 °C: 350.7190046 V
Voltage for Gain 200: T = +20 °C: 390.6216007 V     T = -25 °C: 354.8159756 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.473261149 V-1     T = -25 °C: 4.774677099 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.733366534 V-1     T = -25 °C: 9.777333875 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.18461041 V-1     T = -25 °C: 15.84919444 V-1
Break-through voltage: T = +20 °C: 405.8652619 V     T = -25 °C: 369.7667177 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:59:04 CET jreher Updated box and position via API.
03. Feb 2021 18:24:34 CET jreher Updated box and position via API.
07. Oct 2020 12:12:59 CEST jreher Assigned to capsule by script
17. Aug 2020 15:53:25 CEST jreher Updated box and position via API.
11. Aug 2020 17:38:47 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:43:33 CET jreher Updated APD location via API.
25. Nov 2019 17:17:30 CET jreher Updated box and position via API.
10. Sep 2019 11:23:06 CEST jgrochowski Updated APD batch assignment via API.
04. Sep 2019 12:50:23 CEST markus.moritz
25. Jul 2019 12:13:00 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:47:19 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:31 CET Tobias Corrected dark current unit.
24. May 2018 14:39:23 CEST Tobias Updated location to "Bochum".
18. May 2018 12:04:53 CEST Tobias Imported from Hamamatsu datasheet.