Show Hamamatsu Avalanche Photo Diode 2703030197 - Archived data from Tue, 11. August 2020 17:37:33 CEST


This is all the information about APD 2703030197. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2703030197
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: F09
Break-through voltage: 407 V
Voltage for Gain 100 (T=+25°C): 379.2 V
Dark current: 11.7 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 75
Position in Box: 27
EP1 batch: 57
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 379.0619954 V     T = -25 °C: 343.756734 V
Voltage for Gain 150: T = +20 °C: 386.8822436 V     T = -25 °C: 351.1547342 V
Voltage for Gain 200: T = +20 °C: 391.2398993 V     T = -25 °C: 355.2889102 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.61797125 V-1     T = -25 °C: 4.757171079 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.105064177 V-1     T = -25 °C: 9.304763628 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.1327468 V-1     T = -25 °C: 14.81993865 V-1
Break-through voltage: T = +20 °C: 406.8486691 V     T = -25 °C: 370.6510155 V
   
Notes:


Version history

Time Author Change comment
15. Feb 2021 15:39:33 CET jreher Assigned to capsule by script
05. Feb 2021 10:57:58 CET jreher Updated box and position via API.
03. Feb 2021 18:23:30 CET jreher Updated box and position via API.
18. Dec 2020 14:01:06 CET jreher Updated box and position via API.
11. Aug 2020 17:37:33 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:42:04 CET jreher Updated APD location via API.
25. Nov 2019 17:16:52 CET jreher Updated box and position via API.
06. Sep 2019 13:11:41 CEST spankonin Updated APD batch assignment via API.
03. Sep 2019 11:41:42 CEST markus.moritz
08. Jul 2019 14:55:25 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:46:14 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:16 CET Tobias Corrected dark current unit.
24. May 2018 14:39:23 CEST Tobias Updated location to "Bochum".
18. May 2018 12:02:17 CEST Tobias Imported from Hamamatsu datasheet.