Serial: 2608029740
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C10
Break-through voltage: 403 V
Voltage for Gain 100 (T=+25°C): 374.8 V
Dark current: 8.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 215
Position in Box: 41
EP1 batch: 50
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 374.9831033 V     T = -25 °C: 340.3188625 V
Voltage for Gain 150: T = +20 °C: 382.7366816 V     T = -25 °C: 347.5623136 V
Voltage for Gain 200: T = +20 °C: 387.0628422 V     T = -25 °C: 351.5998852 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.694948378 V-1     T = -25 °C: 4.930577376 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.304831364 V-1     T = -25 °C: 9.16179962 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.52842277 V-1     T = -25 °C: 16.49262786 V-1
Break-through voltage: T = +20 °C: 402.7888357 V     T = -25 °C: 366.7412088 V
   
Notes:


Version history

Time Author Change comment
03. May 2021 10:24:30 CEST oafedulidis Updated box and position via API.
05. Feb 2021 10:57:16 CET jreher Updated box and position via API.
03. Feb 2021 18:22:48 CET jreher Updated box and position via API.
11. Aug 2020 17:39:46 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:41:01 CET jreher Updated APD location via API.
25. Nov 2019 17:16:22 CET jreher Updated box and position via API.
17. Sep 2019 11:30:58 CEST jgrochowski Updated APD batch assignment via API.
04. Sep 2019 13:31:33 CEST markus.moritz
08. Jul 2019 14:53:19 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:45:29 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:06 CET Tobias Corrected dark current unit.
24. May 2018 14:39:23 CEST Tobias Updated location to "Bochum".
18. May 2018 12:00:49 CEST Tobias Imported from Hamamatsu datasheet.