RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2410026680 - Archived data from Wed, 03. February 2021 18:15:45 CET


This is all the information about APD 2410026680. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2410026680
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: B06
Break-through voltage: 413 V
Voltage for Gain 100 (T=+25°C): 384.2 V
Dark current: 5.4 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 174
Position in Box: 44
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 12. Nov 2018
Sent for analysis after irradiation: 26. Nov 2018
Return for assembly: none
   
Irradiation:  
Date: 22. Nov 2018
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 23. Nov 2018
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 385.0845959 V     T = -25 °C: 349.436168 V
Voltage for Gain 150: T = +20 °C: 392.9614821 V     T = -25 °C: 356.9525667 V
Voltage for Gain 200: T = +20 °C: 397.3637778 V     T = -25 °C: 361.1686395 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.405663335 V-1     T = -25 °C: 4.851161108 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.125823765 V-1     T = -25 °C: 9.53203162 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.4535748 V-1     T = -25 °C: 14.5735746 V-1
Break-through voltage: T = +20 °C: 411.894497 V     T = -25 °C: 375.5639881 V
   
Notes: foam


Version history

Time Author Change comment
26. Apr 2021 15:23:01 CEST oafedulidis Updated box and position via API.
05. Feb 2021 10:49:35 CET jreher Updated box and position via API.
03. Feb 2021 18:15:45 CET jreher Updated box and position via API.
11. Aug 2020 17:22:05 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:31:54 CET jreher Updated APD location via API.
25. Nov 2019 17:12:00 CET jreher Updated box and position via API.
04. Jul 2019 11:08:07 CEST jreher Updated APD location via API.
12. Jun 2019 16:46:28 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:31:23 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 15:03:36 CEST jreher Updated APD batch assignment via API.
03. Jan 2019 00:13:02 CET Tobias Corrected dark current unit.
26. Nov 2018 12:16:44 CET markus.moritz
12. Jan 2018 13:16:57 CET Tobias Imported from Hamamatsu datasheet.