RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2404026216 - Archived data from Tue, 11. August 2020 17:21:05 CEST


This is all the information about APD 2404026216. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2404026216
Type: Hamamatsu Avalanche Photo Diode
Detector: assigned to 2404026216/2412026827
Unit: #1006 (barcode 1309009527)
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: blue
   
Manufacturer information:  
Wafer position: G09
Break-through voltage: 410 V
Voltage for Gain 100 (T=+25°C): 381.2 V
Dark current: 3.7 nA
   
Screening Logistics:  
Available: No
Storage Box: 8
Position in Box: 34
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 12. Nov 2018
Sent for analysis after irradiation: 26. Nov 2018
Return for assembly: none
   
Irradiation:  
Date: 22. Nov 2018
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 23. Nov 2018
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 381.0378177 V     T = -25 °C: 345.6962781 V
Voltage for Gain 150: T = +20 °C: 388.8932449 V     T = -25 °C: 353.1272848 V
Voltage for Gain 200: T = +20 °C: 393.2685882 V     T = -25 °C: 357.3013897 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.62047367 V-1     T = -25 °C: 4.666412722 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.134182547 V-1     T = -25 °C: 9.397270293 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.30181034 V-1     T = -25 °C: 14.83793456 V-1
Break-through voltage: T = +20 °C: 408.9255511 V     T = -25 °C: 372.7883376 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:48:47 CET jreher Updated box and position via API.
03. Feb 2021 18:14:57 CET jreher Updated box and position via API.
11. Aug 2020 17:21:05 CEST jreher Updated APD characteristics via API.
31. Mar 2020 08:44:08 CEST jreher Assigned to capsule by script
13. Feb 2020 15:25:31 CET jreher Updated box and position via API.
27. Nov 2019 19:30:48 CET jreher Updated APD location via API.
25. Nov 2019 17:11:32 CET jreher Updated box and position via API.
04. Jul 2019 11:05:54 CEST jreher Updated APD location via API.
12. Jun 2019 16:46:01 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:30:56 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 15:01:54 CEST jreher Updated APD batch assignment via API.
03. Jan 2019 00:12:50 CET Tobias Corrected dark current unit.
26. Nov 2018 12:23:13 CET markus.moritz
26. Nov 2018 11:43:47 CET markus.moritz
16. Nov 2018 11:48:43 CET markus.moritz
12. Jan 2018 13:16:50 CET Tobias Imported from Hamamatsu datasheet.