Serial: 2403026110
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C03
Break-through voltage: 416 V
Voltage for Gain 100 (T=+25°C): 387.5 V
Dark current: 7.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 169
Position in Box: 48
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 24. Jul 2018
Sent for analysis after irradiation: 21. Aug 2018
Return for assembly: none
   
Irradiation:  
Date: 16. Aug 2018
Dose used: 30 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 17. Aug 2018
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 387.3236968 V     T = -25 °C: 351.351062 V
Voltage for Gain 150: T = +20 °C: 395.1800763 V     T = -25 °C: 358.851784 V
Voltage for Gain 200: T = +20 °C: 399.5620869 V     T = -25 °C: 363.0571101 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.481345915 V-1     T = -25 °C: 4.663904457 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.940486551 V-1     T = -25 °C: 8.873084881 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.61158094 V-1     T = -25 °C: 14.7540679 V-1
Break-through voltage: T = +20 °C: 415.6879374 V     T = -25 °C: 378.8170267 V
   
Notes: foam


Version history

Time Author Change comment
26. Apr 2021 14:28:35 CEST oafedulidis Updated box and position via API.
05. Feb 2021 10:47:36 CET jreher Updated box and position via API.
03. Feb 2021 18:14:04 CET jreher Updated box and position via API.
11. Aug 2020 17:20:00 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:28:41 CET jreher Updated APD location via API.
25. Nov 2019 17:10:57 CET jreher Updated box and position via API.
25. Nov 2019 16:56:05 CET jreher Updated box and position via API.
03. Jul 2019 20:03:17 CEST jreher Updated APD location via API.
13. Jun 2019 11:23:41 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:45:30 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:30:25 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:30:05 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 14:55:15 CEST jreher Updated APD batch assignment via API.
03. Jan 2019 00:12:47 CET Tobias Corrected dark current unit.
21. Aug 2018 09:10:24 CEST markus.moritz
20. Aug 2018 14:49:45 CEST markus.moritz
12. Jan 2018 13:16:48 CET Tobias Imported from Hamamatsu datasheet.