RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2320025881 - Archived data from Wed, 03. February 2021 18:14:31 CET


This is all the information about APD 2320025881. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2320025881
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D01
Break-through voltage: 409 V
Voltage for Gain 100 (T=+25°C): 380.1 V
Dark current: 5.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 26
Position in Box: 37
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 21. Sep 2018
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 379.7632277 V     T = -25 °C: 344.5758252 V
Voltage for Gain 150: T = +20 °C: 387.7010491 V     T = -25 °C: 352.0251898 V
Voltage for Gain 200: T = +20 °C: 392.1183761 V     T = -25 °C: 356.226528 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.637661875 V-1     T = -25 °C: 4.698585832 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.200294307 V-1     T = -25 °C: 9.306731867 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.58596361 V-1     T = -25 °C: 14.65530652 V-1
Break-through voltage: T = +20 °C: 407.8543426 V     T = -25 °C: 371.6190772 V
   
Notes:


Version history

Time Author Change comment
21. Apr 2021 14:49:14 CEST oafedulidis Updated box and position via API.
05. Feb 2021 10:48:10 CET jreher Updated box and position via API.
03. Feb 2021 18:14:31 CET jreher Updated box and position via API.
11. Aug 2020 17:20:31 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:30:14 CET jreher Updated APD location via API.
25. Nov 2019 17:11:16 CET jreher Updated box and position via API.
04. Jul 2019 11:05:29 CEST jreher Updated APD location via API.
04. Jul 2019 10:44:31 CEST jreher Updated APD location via API.
12. Jun 2019 16:45:46 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:30:41 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 15:00:44 CEST jreher Updated APD batch assignment via API.
03. Jan 2019 00:12:40 CET Tobias Corrected dark current unit.
26. Sep 2018 12:45:12 CEST markus.moritz
12. Jan 2018 13:16:44 CET Tobias Imported from Hamamatsu datasheet.