RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2319025806 - Archived data from Tue, 11. August 2020 17:20:20 CEST


This is all the information about APD 2319025806. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2319025806
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E06
Break-through voltage: 408 V
Voltage for Gain 100 (T=+25°C): 379.8 V
Dark current: 3.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 4
Position in Box: 2
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 21. Sep 2018
Sent for analysis after irradiation: 02. Oct 2018
Return for assembly: none
   
Irradiation:  
Date: 27. Sep 2018
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: 28. Sep 2018
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 380.2814073 V     T = -25 °C: 344.5654068 V
Voltage for Gain 150: T = +20 °C: 388.0780819 V     T = -25 °C: 351.9426831 V
Voltage for Gain 200: T = +20 °C: 392.4093254 V     T = -25 °C: 356.087073 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.337247259 V-1     T = -25 °C: 4.619207261 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.796790926 V-1     T = -25 °C: 9.444124086 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.66428905 V-1     T = -25 °C: 15.11391105 V-1
Break-through voltage: T = +20 °C: 407.7689516 V     T = -25 °C: 371.562571 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:48:01 CET jreher Updated box and position via API.
03. Feb 2021 18:14:22 CET jreher Updated box and position via API.
11. Aug 2020 17:20:20 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:30:02 CET jreher Updated APD location via API.
25. Nov 2019 17:11:11 CET jreher Updated box and position via API.
04. Jul 2019 11:05:19 CEST jreher Updated APD location via API.
04. Jul 2019 10:44:21 CEST jreher Updated APD location via API.
12. Jun 2019 16:45:40 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:30:35 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 14:59:12 CEST jreher Updated APD batch assignment via API.
03. Jan 2019 00:12:38 CET Tobias Corrected dark current unit.
02. Oct 2018 15:58:48 CEST markus.moritz
26. Sep 2018 11:04:28 CEST markus.moritz
12. Jan 2018 13:16:43 CET Tobias Imported from Hamamatsu datasheet.