Show Hamamatsu Avalanche Photo Diode 2519028991 - Archived data from Wed, 03. February 2021 18:22:31 CET


This is all the information about APD 2519028991. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2519028991
Type: Hamamatsu Avalanche Photo Diode
Detector: assigned to 2519028991/2512028419
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: blue
   
Manufacturer information:  
Wafer position: B13
Break-through voltage: 416 V
Voltage for Gain 100 (T=+25°C): 387.2 V
Dark current: 3.3 nA
   
Screening Logistics:  
Available: No
Storage Box: 67
Position in Box: 10
EP1 batch: 46
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jul 2019
Sent for analysis after irradiation: 19. Jul 2019
Return for assembly: none
   
Irradiation:  
Date: 16. Jul 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 17. Jul 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 387.3754789 V     T = -25 °C: 351.3604127 V
Voltage for Gain 150: T = +20 °C: 395.2416678 V     T = -25 °C: 358.8796493 V
Voltage for Gain 200: T = +20 °C: 399.6118343 V     T = -25 °C: 363.0931099 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.438471324 V-1     T = -25 °C: 4.687863126 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.718126648 V-1     T = -25 °C: 9.382837577 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.22046845 V-1     T = -25 °C: 14.82635843 V-1
Break-through voltage: T = +20 °C: 414.7271729 V     T = -25 °C: 378.2685621 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:56:57 CET jreher Updated box and position via API.
03. Feb 2021 18:22:31 CET jreher Updated box and position via API.
07. Oct 2020 12:17:47 CEST jreher Assigned to capsule by script
17. Aug 2020 15:50:49 CEST jreher Updated box and position via API.
11. Aug 2020 17:33:30 CEST jreher Updated APD characteristics via API.
20. Feb 2020 13:35:14 CET jreher Updated box and position via API.
27. Nov 2019 19:40:37 CET jreher Updated APD location via API.
25. Nov 2019 17:16:11 CET jreher Updated box and position via API.
05. Aug 2019 16:54:40 CEST jreher Updated APD batch assignment via API.
29. Jul 2019 11:59:19 CEST markus.moritz
05. Jul 2019 13:45:11 CEST jreher Updated APD location via API.
01. Jul 2019 12:50:03 CEST jgrochowski Updated APD batch assignment via API.
03. Jan 2019 00:12:37 CET Tobias Corrected dark current unit.
12. Jan 2018 13:12:15 CET Tobias Imported from Hamamatsu datasheet.