RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2514028633 - Archived data from Fri, 05. February 2021 10:56:10 CET


This is all the information about APD 2514028633. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2514028633
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E06
Break-through voltage: 409 V
Voltage for Gain 100 (T=+25°C): 380.2 V
Dark current: 6.6 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 61
Position in Box: 10
EP1 batch: 36
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jul 2019
Sent for analysis after irradiation: 19. Jul 2019
Return for assembly: none
   
Irradiation:  
Date: 16. Jul 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 17. Jul 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 379.8584974 V     T = -25 °C: 345.3906574 V
Voltage for Gain 150: T = +20 °C: 387.6826971 V     T = -25 °C: 352.5939517 V
Voltage for Gain 200: T = +20 °C: 392.0501426 V     T = -25 °C: 356.6157284 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.407943171 V-1     T = -25 °C: 4.913028418 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.677767017 V-1     T = -25 °C: 9.453321007 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.25557932 V-1     T = -25 °C: 15.38995272 V-1
Break-through voltage: T = +20 °C: 407.8174001 V     T = -25 °C: 371.6246088 V
   
Notes:


Version history

Time Author Change comment
15. Apr 2021 16:22:07 CEST oafedulidis Assigned to capsule by script
16. Feb 2021 12:28:30 CET jreher Updated box and position via API.
05. Feb 2021 10:56:10 CET jreher Updated box and position via API.
03. Feb 2021 18:21:44 CET jreher Updated box and position via API.
11. Aug 2020 17:32:32 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:39:31 CET jreher Updated APD location via API.
25. Nov 2019 17:15:41 CET jreher Updated box and position via API.
01. Aug 2019 12:13:05 CEST spankonin Updated APD batch assignment via API.
24. Jul 2019 10:06:33 CEST markus.moritz
12. Jul 2019 13:55:38 CEST jreher Updated APD location via API.
01. Jul 2019 14:24:51 CEST spankonin Updated APD batch assignment via API.
03. Jan 2019 00:12:27 CET Tobias Corrected dark current unit.
12. Jan 2018 13:12:10 CET Tobias Imported from Hamamatsu datasheet.