RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2512028451 - Archived data from Tue, 11. August 2020 17:32:03 CEST


This is all the information about APD 2512028451. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2512028451
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: B11
Break-through voltage: 408 V
Voltage for Gain 100 (T=+25°C): 379.1 V
Dark current: 5.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 180
Position in Box: 9
EP1 batch: 31
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jul 2019
Sent for analysis after irradiation: 19. Jul 2019
Return for assembly: none
   
Irradiation:  
Date: 16. Jul 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 17. Jul 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 379.1475998 V     T = -25 °C: 344.1089552 V
Voltage for Gain 150: T = +20 °C: 386.996821 V     T = -25 °C: 351.4576846 V
Voltage for Gain 200: T = +20 °C: 391.3687303 V     T = -25 °C: 355.5895883 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.580336679 V-1     T = -25 °C: 4.966975301 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.101919114 V-1     T = -25 °C: 9.198123708 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.23752459 V-1     T = -25 °C: 14.62273462 V-1
Break-through voltage: T = +20 °C: 406.8170966 V     T = -25 °C: 370.726338 V
   
Notes:


Version history

Time Author Change comment
26. Oct 2021 09:59:29 CEST oafedulidis Assigned to capsule by script
10. May 2021 14:00:13 CEST oafedulidis Updated box and position via API.
05. Feb 2021 11:11:29 CET jreher Updated box and position via API.
11. Aug 2020 17:32:03 CEST jreher Updated APD characteristics via API.
27. Nov 2019 20:00:48 CET jreher Updated APD location via API.
25. Nov 2019 17:25:03 CET jreher Updated box and position via API.
30. Jul 2019 15:19:12 CEST spankonin Updated APD batch assignment via API.
23. Jul 2019 10:56:30 CEST markus.moritz
05. Jul 2019 14:50:37 CEST jreher Updated APD location via API.
24. Jun 2019 16:13:00 CEST spankonin Updated APD batch assignment via API.
03. Jan 2019 00:12:22 CET Tobias Corrected dark current unit.
12. Jan 2018 13:12:07 CET Tobias Imported from Hamamatsu datasheet.