RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2502027659 - Archived data from Mon, 01. April 2019 14:13:50 CEST


This is all the information about APD 2502027659. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2502027659
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: unknown
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E08
Break-through voltage: 409 V
Voltage for Gain 100 (T=+25°C): 380.6 V
Dark current: 4.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 59
Position in Box: 31
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 19. Feb 2019
Sent for analysis after irradiation: 01. Apr 2019
Return for assembly: none
   
Irradiation:  
Date: 27. Mar 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 27. Mar 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 150: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 200: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 100: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 150: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 200: T = +20 °C: none     T = -25 °C: none
Break-through voltage: T = +20 °C: none     T = -25 °C: none
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:55:57 CET jreher Updated box and position via API.
03. Feb 2021 18:21:31 CET jreher Updated box and position via API.
11. Aug 2020 17:29:11 CEST jreher Updated APD characteristics via API.
31. Mar 2020 08:53:32 CEST jreher Assigned to capsule by script
13. Feb 2020 14:23:10 CET jreher Updated box and position via API.
27. Nov 2019 19:39:10 CET jreher Updated APD location via API.
25. Nov 2019 17:15:33 CET jreher Updated box and position via API.
15. Jul 2019 13:02:33 CEST spankonin Updated APD batch assignment via API.
04. Jul 2019 11:13:13 CEST jreher Updated APD location via API.
21. Jun 2019 16:14:19 CEST spankonin Updated APD batch assignment via API.
01. Apr 2019 14:13:50 CEST markus.moritz
03. Jan 2019 00:12:01 CET Tobias Corrected dark current unit.
12. Jan 2018 13:11:56 CET Tobias Imported from Hamamatsu datasheet.