RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2418027348 - Archived data from Wed, 03. February 2021 18:17:03 CET


This is all the information about APD 2418027348. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2418027348
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: B11
Break-through voltage: 411 V
Voltage for Gain 100 (T=+25°C): 383.9 V
Dark current: 7 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 24
Position in Box: 33
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jan 2019
Sent for analysis after irradiation: 25. Jan 2019
Return for assembly: none
   
Irradiation:  
Date: 21. Jan 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 22. Jan 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 385.066238 V     T = -25 °C: 349.2927268 V
Voltage for Gain 150: T = +20 °C: 392.8472795 V     T = -25 °C: 356.7029411 V
Voltage for Gain 200: T = +20 °C: 397.1394963 V     T = -25 °C: 360.8914926 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.794787729 V-1     T = -25 °C: 4.649823124 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.191251052 V-1     T = -25 °C: 9.498299956 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.1767141 V-1     T = -25 °C: 15.62759005 V-1
Break-through voltage: T = +20 °C: 410.675284 V     T = -25 °C: 374.8551412 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:50:56 CET jreher Updated box and position via API.
03. Feb 2021 18:17:03 CET jreher Updated box and position via API.
11. Aug 2020 17:23:39 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:33:44 CET jreher Updated APD location via API.
25. Nov 2019 17:12:47 CET jreher Updated box and position via API.
04. Jul 2019 11:09:29 CEST jreher Updated APD location via API.
12. Jun 2019 16:47:13 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:32:07 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 15:12:28 CEST jreher Updated APD batch assignment via API.
25. Jan 2019 12:33:16 CET markus.moritz
03. Jan 2019 00:11:51 CET Tobias Corrected dark current unit.
12. Jan 2018 13:11:52 CET Tobias Imported from Hamamatsu datasheet.