RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2410026711 - Archived data from Wed, 12. June 2019 15:03:45 CEST


This is all the information about APD 2410026711. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2410026711
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: unknown
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C02
Break-through voltage: 412 V
Voltage for Gain 100 (T=+25°C): 383.5 V
Dark current: 4.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 15
Position in Box: 16
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 12. Nov 2018
Sent for analysis after irradiation: 13. Dec 2018
Return for assembly: none
   
Irradiation:  
Date: 07. Dec 2018
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 10. Dec 2018
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 150: T = +20 °C: none     T = -25 °C: none
Voltage for Gain 200: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 100: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 150: T = +20 °C: none     T = -25 °C: none
Gain/Voltage slope at M = 200: T = +20 °C: none     T = -25 °C: none
Break-through voltage: T = +20 °C: none     T = -25 °C: none
   
Notes:


Version history

Time Author Change comment
29. Apr 2021 17:03:50 CEST oafedulidis Assigned to capsule by script
16. Feb 2021 12:28:45 CET jreher Updated box and position via API.
05. Feb 2021 10:49:40 CET jreher Updated box and position via API.
03. Feb 2021 18:15:50 CET jreher Updated box and position via API.
11. Aug 2020 17:22:10 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:32:03 CET jreher Updated APD location via API.
25. Nov 2019 17:12:04 CET jreher Updated box and position via API.
04. Jul 2019 11:08:14 CEST jreher Updated APD location via API.
12. Jun 2019 16:46:31 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:31:26 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 15:03:45 CEST jreher Updated APD batch assignment via API.
03. Jan 2019 00:11:33 CET Tobias Corrected dark current unit.
13. Dec 2018 11:44:33 CET markus.moritz
23. Nov 2018 14:18:12 CET markus.moritz
12. Jan 2018 13:11:42 CET Tobias Imported from Hamamatsu datasheet.