Subdetector specification:  
Serial: 2304024454
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: G09
Break-through voltage: 409 V
Voltage for Gain 100 (T=+25°C): 382.1 V
Dark current: 6.4 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 252
Position in Box: 40
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 381.4078145 V     T = -25 °C: 346.0680961 V
Voltage for Gain 150: T = +20 °C: 389.1751843 V     T = -25 °C: 353.3903735 V
Voltage for Gain 200: T = +20 °C: 393.500459 V     T = -25 °C: 357.4924992 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.508547822 V-1     T = -25 °C: 4.911060385 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.875931426 V-1     T = -25 °C: 9.22965719 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.65207466 V-1     T = -25 °C: 16.53200936 V-1
Break-through voltage: T = +20 °C: 409.7339043 V     T = -25 °C: 372.1824691 V
   
Notes:


Version history

Time Author Change comment
21. Apr 2021 14:52:58 CEST oafedulidis Updated box and position via API.
05. Feb 2021 11:15:46 CET jreher Updated box and position via API.
11. Aug 2020 17:44:16 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:26:26 CEST jreher Updated box and position via API.
27. Nov 2019 20:06:38 CET jreher Updated APD location via API.
25. Nov 2019 17:27:27 CET jreher Updated box and position via API.
31. Oct 2019 17:11:35 CET spankonin Updated APD batch assignment via API.
31. Oct 2019 17:00:18 CET spankonin Updated APD location via API.
23. Jun 2016 11:58:02 CEST Tobias Imported from Hamamatsu datasheet.